Close Menu
NewsFile GH
  • Home
  • Local News
  • Politics
  • Business
  • Sports
  • Showbiz
  • Odd News
  • Opinion
What's Hot

Assin Fosu Assembly commends Zoomlion’s waste collection efficiency

Gov’t proposes AI Authority at National AI Strategy launch

No contractor owed a pesewa on Big Push projects – Agbodza

Facebook X (Twitter) Instagram
Trending
  • Assin Fosu Assembly commends Zoomlion’s waste collection efficiency
  • Gov’t proposes AI Authority at National AI Strategy launch
  • No contractor owed a pesewa on Big Push projects – Agbodza
  • Fire at GRIDCo’s Akosombo substation leaves parts of country without power
  • Carlos Queiroz outdoored
  • Ghana risks losing up to $2 bn if power outages persist, warns ASEC
  • My eight True Dare: ICUMS vs Truedare – Why is Truedare more expensive than ICUMS?
  • Parliament’s Energy Committee commends NPA’s openness
Facebook X (Twitter) Instagram
NewsFile GH
Demo
  • Home
  • Local News

    Assin Fosu Assembly commends Zoomlion’s waste collection efficiency

    April 24, 2026

    Earth Day 2026: ActionAid Ghana flags coastal pollution & climate risks as national concern

    April 23, 2026

    Chief of Staff participates in Harvard Ministerial Leadership Programme to strengthen gov’t delivery

    April 22, 2026

    GIS cracks down on migrant begging networks in Kumasi; nearly 400 children grabbed

    April 22, 2026

    Bawumia confers with EU Ambassadors in Accra

    April 21, 2026
  • Politics

    APL survey: Asiedu Nketia narrowly leads Julius Debrah in NDC 2028 race

    April 21, 2026

    NPP Bono Region Chairman Abronye flown abroad for ‘urgent’ medical care

    April 18, 2026

    Former NPP MP Paul Twum-Barimah defends High Court ruling on OSP powers

    April 17, 2026

    Chris Boadi-Mensah has doubled salary as NPRA boss without board approval – Assafuah alleges

    April 16, 2026

    11 staff transfers under Boadi-Mensah cost pensioners nearly GH¢1m – Assafuah alleges

    April 16, 2026
  • Business

    No contractor owed a pesewa on Big Push projects – Agbodza

    April 24, 2026

    Fire at GRIDCo’s Akosombo substation leaves parts of country without power

    April 23, 2026

    Ghana risks losing up to $2 bn if power outages persist, warns ASEC

    April 23, 2026

    Parliament’s Energy Committee commends NPA’s openness

    April 23, 2026

    NPA CEO champions women empowerment at launch of NAPET Ladies Week 2026

    April 21, 2026
  • Sports

    Carlos Queiroz outdoored

    April 23, 2026

    Asante Kotoko’s interim coach Yaw Owusu resigns after barely two months

    April 21, 2026

    New Black Stars coach Carlos Queiroz arrives on Thursday for unveiling

    April 20, 2026

    AFCON 2025: Fresh evidence could strengthen Morocco’s hand at CAS in title dispute with Senegal

    April 19, 2026

    Thomas-Asante’s Coventry City end 25-year Premier League exile after securing promotion

    April 17, 2026
  • Showbiz

    Kwahu Easter a national tourism asset that needs infrastructure support – Mpraeso MP

    March 27, 2026

    Gyankroma Akufo-Addo denies $25m interchange painting claims; threatens legal action

    March 27, 2026

    OnlyFans owner Leonid Radvinsky dies at 43

    March 23, 2026

    Liizzy Gordon sings about the Blood of Jesus

    March 23, 2026

    Medikal vows to make an impact with ‘Red Means Stop’ campaign

    March 13, 2026
  • Odd News

    We had sex in a Chinese hotel, then found we had been broadcast to thousands

    February 6, 2026

    Nsawam Female Prison inmates showcase talents, proving rehabilitation thrives through discipline, culture and self-expression

    January 6, 2026

    Drunk raccoon found passed out on liquor store floor after breaking in

    December 3, 2025

    Search for Malaysia Airlines flight MH370 missing in 2014 to resume

    December 3, 2025

    School bans singing of KPop Demon Hunters songs

    November 17, 2025
  • Opinion

    My eight True Dare: ICUMS vs Truedare – Why is Truedare more expensive than ICUMS?

    April 23, 2026

    Ghana’s Investment Revolution: Open for business, protected for citizens

    April 20, 2026

    What 8 yrs in the wilderness taught me about business in Ghana

    April 20, 2026

    TALKING DRUM: Newtown Building Collapse – The Folly of a Nation!

    April 17, 2026

    After slavery recognition, Africa must break economic chains for real freedom

    March 30, 2026
NewsFile GH
Home»Local News»How ¢1.4m project ballooned to ¢7.9m: Foreign Ministry sets record straight
Local News

How ¢1.4m project ballooned to ¢7.9m: Foreign Ministry sets record straight

By newsfileghJanuary 31, 20237 Mins Read
Share Facebook Twitter LinkedIn Email WhatsApp Telegram Copy Link
Share
Facebook Twitter LinkedIn WhatsApp Copy Link Email

The Ministry of Foreign Affairs and Regional Integration has given further explanation to how a project which initial cost was GH¢1,435,728.99 was executed at GH¢7,967,886.57.

The contract for the rehabilitation of Adu Lodge Guest House, which is a presidential lodge facility, was awarded to International Development Resources on March 15, 2007.

Appearing before the Public Accounts Committee (PAC) on Friday, January 20, 2023, the Acting Chief Director of the Ministry, Ambassador Ramses Joseph said the project was revisited in March 2019 and upon the request of the consultant, was re-valued to GH¢7,967,886.57 for the same contractor to execute.

He had attributed the delay in project execution to the ill health of the contractor.

But Ministry of Foreign Affairs says the explanation offered by the Acting Director was “inaccurate”.

“The Ministry wishes to state on record that, the delay in getting the project completed had been occasioned by a number of factors, including the redesign and delayed release of funds, delayed certification, and delayed payment of those certificates issued to the contractor by AESL.

“As a result of the delay, the contract sum increased in correlation to increased inflation and currency depreciation impacting adversely on material cost,” the Ministry said in a statement on Monday.

The Ministry’s statement also gave detailed account of the project.

The initial comprised: Refurbishment of Block A; Refurbishment of Block B; Refurbishment of Block C; External works; Electrical installation works; 2 Boys Quarters structures; Security gatehouse; Swimming pool; Fire detection installation; and Air-conditioning system.

After it was redesigned, the following was included: Construction of a Laundry block; Construction of a Conference Block; Construction of a kitchen block; Construction of a pool house; Generator platform; Water storage tank and platform; Borehole drilling and treatment; VOIP intercom and data networking; Installation of fitted kitchen; and Close Circuit Television.

Find the Ministry’s full statement below

REJOINDER: “MINISTRY OF FOREIGN AFFAIRS SPENDS 7.9 MILLION CEDIS ON A 1.4 MILLION CEDIS PROJECT BECAUSE  THE CONTRACTOR FELL ILL – CHIEF DIRECTOR”

While noting that the submission was inaccurate, the Ministry takes the opportunity to apprise the public about the extent of works and details of events that led to the delay and increased cost between the years 2007 and 2021.

Adu Lodge is a presidential lodge facility that consists of 3 buildings that were used to host various sizes of high-level delegations with the primary objective of saving the taxpayer avoidable expenses. This was the function of the Adu Lodge facility for decades until it was closed, originally for rebuilding and later revised for renovation.

The original award to Messrs International Development Resources (IDR) on 15. March, 2007 by the Architectural Engineering Services Limited (AESL) was to demolish the originally existing 3 buildings that constituted the Lodge, at the time, and construct a new building of twelve (12) bedroom at a contract sum of Fourteen Billion. Three Hundred and Fifty-Seven Million, Two Hundred and Eighty-Nine Thousand, Seven Hundred and Seventy old Ghana cedis (14,357,289.77), equivalent to One Million, Four Hundred and Thirty-Five Thousand, Seven Hundred and Twenty-Eight new Ghana Cedis, Ninety-Eight Pesewas (GH01,435.728.98) after the redenomination of the Cedi in July 2007.

The contract sum was, however, revised in October, 2011 to an amount of Four Million, Four

Hundred and Thirty-Two Thousand, Five Hundred and Fifty-Eight Ghana Cedis, Seventy pesewas

(GH4,432,558.70). This time, the project had been reviewed to rather renovate the existing facilities and build additional ones for expansion and to create room for other ancillary facilities.

The revised bill of Quantities from AESL covered the under-listed works:

  • Refurbishment of Block A
  • Refurbishment of Block B
  • Refurbishment of Block C
  • External works
  • Electrical installation works
  • 2 Boys Quarters structures
  • Security gatehouse
  • Swimming pool
  • Fire detection installation
  • Air-conditioning system

Unfortunately, the project stalled completely from the period 2009 to 2017 mainly due to the inability of the contractor to continue to prefinance the project as a result of the lack of reimbursement for expenditure already incurred. Indeed, the bank accounts of IDR were garnisheed for its inability to pay back bank loans the company had taken to prefinance the project on schedule.

On her assumption of office in the year 2017. Honourable Shirley Ayorkor Botchwey, the Minister for Foreign Affairs and Regional Integration called for the review of the contract which was later re-awarded to save the country the already invested funds and put the facility to its originally intended use.

The Ministry, therefore, invited Public Works Department (PWD) Prestige to take over the supervision of the project in December, 2017, after 6 years of inactivity. This necessitated the need to revisit, ascertain and revise the outstanding works on the project. PWD Prestige’s assessment revealed that the value of outstanding works from details above was Five Million, Eight Hundred and Seventy-Five Thousand, Three Hundred and Eighteen Ghana Cedis, Ninety-Six pesewas (GH¢5,875,318.96) per the prevailing market prices as of 16th January, 2018.

Not long after this, a site meeting was held, and it was decided that there was a need to include other works which did not form part of the initial Bills of Quantities. The Department was, once again, tasked to review the Bill of Quantities on 170 January. 2019 taking into consideration, the outstanding works including the new structures. The General Summary of the works amounted to Eight Million, Three Hundred and Thirty Thousand, Sixty-Three Cedis, Twenty-Three Pesewas (GH¢8,330,063.23). Newly measured works that were added to the existing project comprised the following:

  • Construction of a Laundry block
  • Construction of a Conference Block
  • Construction of a kitchen block
  • Construction of a pool house
  • Generator platform
  • Water storage tank and platform
  • Borehole drilling and treatment VOIP intercom and data networking
  • Installation of fitted kitchen
  • Close Circuit Television

The Ministry duly obtained the procedural approval of the Public Procurement Authority (PPA) and transmitted same to the PWD. Prestige to enable the revival of the project. It is worth noting that the PPA, while granting the approval, directed that the Fifteen (15) % of the Contingency sum be reduced to Ten (10) %. This brought about a reduction of the proposed contract sum to Seven Million, Nine Hundred and Sixty-Seven Thousand, Eight Hundred and Eighty-Six Ghana Cedis Fifty-Seven Pesewas (GH¢7,967.886.57) as the new contract sum.

The above-listed and reviewed works were duly completed and handed over to the Ministry in October. 2021. Payment of work done was honoured at various stages until completion with the exception of the retention amount of One Hundred and Fifty-Five Thousand, Three Hundred and Thirty-Eight Ghana Cedis. Ninety-Three pesewas (0E10155,338.93).

Throughout the lifespan of the project, Sixteen Interim Payment Certificates were raised. Five out of the Sixteen were valued and raised by AESL and the remaining 11 by PWD Prestige after taking over the project.

The Ministry wishes to state on record that, the delay in getting the project completed had been occasioned by a number of factors, including the redesign and delayed release of funds, delayed certification, and delayed payment of those certificates issued to the contractor by AESL As a result of the delay, the contract sum increased in correlation to increased inflation and currency depreciation impacting adversely on material cost.

While the Ministry seeks to assure the general public of every effort to sustain the prudent management of resources entrusted to it by the people of Ghana, it also hopes that the foregoing clears any misunderstanding that resulted from the submission made to the Public Accounts Committee of Parliament.

Share. Facebook Twitter LinkedIn Email Copy Link WhatsApp

Related Posts

Minister for foreign affairs receives the open letters of three envoys

February 19, 2026By newsfilegh2 Mins Read

iShowSpeed wraps African tour, calls experience “Life-Changing”

January 28, 2026By Fiifi Sey1 Min Read

Ghana, China sign tourism and culture partnership under 24-Hour Economy agenda

January 21, 2026By Fiifi Sey1 Min Read
Follow Us
  • Facebook
  • Twitter
  • Instagram
  • YouTube
Recent Posts
  • Assin Fosu Assembly commends Zoomlion’s waste collection efficiency
  • Gov’t proposes AI Authority at National AI Strategy launch
  • No contractor owed a pesewa on Big Push projects – Agbodza
  • Fire at GRIDCo’s Akosombo substation leaves parts of country without power
  • Carlos Queiroz outdoored
  • Ghana risks losing up to $2 bn if power outages persist, warns ASEC
Top Posts

Assin Fosu Assembly commends Zoomlion’s waste collection efficiency

Gov’t proposes AI Authority at National AI Strategy launch

No contractor owed a pesewa on Big Push projects – Agbodza

Fire at GRIDCo’s Akosombo substation leaves parts of country without power

About Us
About Us

NewsFile Gh is a comprehensive news portal that delivers up-to-date information on a wide range of topics, including politics, business, sports, entertainment etc. It provides users with real-time news updates accessible anytime and anywhere...

Email Us: news@newsfilegh.com

Facebook X (Twitter) YouTube RSS
Recent

Assin Fosu Assembly commends Zoomlion’s waste collection efficiency

Gov’t proposes AI Authority at National AI Strategy launch

No contractor owed a pesewa on Big Push projects – Agbodza

Most Popular

IS leader in Afghanistan ‘killed’

July 11, 2015

‘Oldest’ Koran found at UK university

July 22, 2015

Gunman in Mahama’s church for court today

July 28, 2015
© 2026 NewsFile GH. All Rights Reserved.
  • Home
  • Politics

Type above and press Enter to search. Press Esc to cancel.